Intro
tentang personal item yg dimuatkan dlm e-page aku ini. Semua
ini hobby dan utk mengisi masa lapang. Tiada niat lain aaaaa...
So, jgn disalahguna! |
Career Objective:
|
Seeking
a field or project engineer position. Offering skills as an
engineer who has an extensive experience and exposure in offshore
construction projects. Graduated from the premier university
in Malaysia, University Of Malaya with B.Eng. Mechanical Hons.
and trained under Shell Malaysia Scholarship Programme. Willing
to pursue career with offshore installation/construction related
company. |
Personal Information |
Contact Num |
: +60173660466 |
E-mail |
: laiman@crest.com.my |
Language |
: Malay, English & Bugese |
DOB |
: 20th March, 1976 |
Race |
: Malay |
Marital Status |
: Single |
Nationality |
: Malaysian (International
Passport) |
Hobbies |
: Swimming & Outdoor Act.
|
Academic & Technical
Qualification |
1995 - 1999 |
: University Of Malaya, Malaysia
(Bachelor Degree of Mechanical Engineering) |
1993 - 1995 |
: Foundation Of Science, University
Of Malaya, Malaysia. |
1991 - 1993 |
: Sek. Berasrama Penuh Lahad
Datu, Sabah, Malaysia (Full Boarding School) |
1988 - 1991 |
: Sek. Men. Keb. Kunak, Sabah,
Malaysia |
1982 - 1988 |
: Sek. Ren. Keb. Mostyn, Kunak,
Sabah, Malaysia. |
Award & Achievement |
1994
|
: 'Anugerah Buku' Foundation
of Science, University Of Malaya, Malaysia. |
1993
|
: 'Biasiswa Cemerlang Negeri
Sabah SPM 93', Sabah State Government, Malaysia |
1993
|
: Best Student of SPM 93, SBP
Lahad Datu, Sabah, Malaysia |
1991
|
: Best Student of SRP 93, SMK
Kunak, Sabah, Malaysia |
1988
|
: Best Student of UPSR 88, SRK
Mostyn, Kunak, Sabah |
Training & Courses |
2003 |
:Risk Assesment Course - DNV
Malaysia |
2002 |
: PTW Applicant Course - Shell
Malaysia, Bintulu. |
2002 |
: Incident Reporting & Investigation
Course - Professional Loss Control |
2002 |
: Emergency Response Plan &
Preparedness - Professional Loss Control |
2002 |
: Under Water Wet Welding Seminar
- Global Offshore Sdn. Bhd. |
2001 |
: ANGSI 2001 Mid-Management HSE
Awarness Workshop - TL Offshore Sdn. Bhd |
2000 |
: Positive Work & Relationship
for Executive - RENONG Training Center |
1999 |
: Basic Offshore Safety and Emergency
Training B.O.S.E.T - Consist Malaysia |
1995 |
: Human Relation & Leadership
Course - Ministry of Youth & Sport Malaysia. |
1993 |
: Elementary Typewriting - Youth
Technical & Commercial Training Center, Sabah. |
Working & Technical
Experieces |
|
Click for exp. on
year : 2003, 2002,
2001, 2000,1999 |
|
|
|
|
|
Company |
: TL
Offshore Sdn. Bhd. |
Position |
: Field Engineer |
Date |
:June 2003 |
Vessel : Osam Dragon |
Client |
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: Pre-Commisioning
of 24" Dia. x 42km HCP/B11DR-A Pipeline. |
|
- Receiving point at B11DR-A.
- Installation of temporary
receiver & test blind.
- Monitoring of pigging &
Hydrotest activities.
|
Company |
: TL
Offshore Sdn. Bhd. |
Position |
: Field Engineer |
Date |
: May - June 2003 |
Vessel : DLB 264 |
Client |
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: 24" Dia. HCP/B11DR-A
42km Pipeline & Installation of risers at HCP & B11DR-A |
|
- Pipelay of 24" Dia.
HCP/B11DR-A 42km pipeline.
- Installation of 24"
risers at HCP & B11DR-A
|
Company |
: TL
Offshore Sdn. Bhd. |
Position |
: Project/Field
Engineer |
Date |
: August 2002 - May
2003 |
Vessel : Hyundai
HDB289 |
Client |
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: Pipeline Repair
of 610mm SELIGI-A To ANDR-A Gas Export Pipeline. |
|
- Involve from the beginning
of project i.e subcontractor technical evaluation.
- Witness the Smart Plug FAT
(Factory Acceptance Test) at PSI headquater in Stavanger,
Norway.
- Pipeline isolation works
i.e launching of PIG train at ANDRA platform, tracking using
isotope detector onboard DP Petani Shamal and final positioning
of Smart Plug at repair location onboard Hyundai HDB289.
- Pipeline lifting & cutting,
installation 4 Flanges, Fabrication of replacement spool.
- Performing the Internal Joint
Testing (IJT) on the field joint and KaMos test on the flange
connection.
- Retrieving of PIG train at
ANDR-A Platform.
|
Company |
: TL
Offshore Sdn. Bhd. |
Position |
: Field Engineer |
Date |
January, 2003 |
Location : ERB West Platform |
Client |
: Petronas
Carigali Sdn. Bhd. (Sabah, Malaysia) |
Project |
Pre-Commissioning
of 6" EWP-A to EWDP-B Pipeline (1st Phase) |
|
- Performing pigging, cleaning
and gauging operation through the pipeline from temporary
pig launcher installed at EWP-A platform to temporary receiver
at EWDP-B Platform.
- Run PIGs i.e. Polybrush,
Bi-Di c/w brush, Bi-Di standard and Bi-Di c/w gauging plate
with 95% of pipeline diameter.
- Running the EGP (Electronic
Geometry Pig) and CDP (Corrosion Detection Pig) intelligent
pig to determint the pipeline condition before hydrotest.
|
|
|
|
Company |
: TL
Offshore Sdn. Bhd. |
Position |
: Field Engineer |
Date |
November, 2002 |
Vessel: Teknik Putra |
Client |
: Petronas
Carigali Sdn. Bhd. (Sabah, Malaysia) |
Project |
MLNG-Tiga - Post
Lay Survey of 30" Dia. x 155km Pipeline from M1DRA to E11RC |
|
- Post lay survey side Scan
Sonar operated on a 50m range from pipeline (Both side of
the pipeline)
- Cross line survey using survey
echo sounder to confirm pipeline exact position.
|
Company |
: TL
Offshore Sdn. Bhd. |
Position |
: Field Engineer/Loadout
Coordinator |
Date |
October, 2002 |
Location: MSE Yard, Pasir
Gudang |
Client |
: Petronas
Carigali Sdn. Bhd. (Sabah, Malaysia) |
Project |
MLNG-Tiga - E11R-C
(West Side) Riser Guard/Emergency Boatlanding Loadout |
|
- Loadout coordinator. Coordinating
vessel movements for boatlanding & its shiploose transportation.
- Towing survey by Berkat Global.
- Monitoring Boatlanding Loadout
to material barge Dynaroy III + Tug boat Destiny III
- Monitoring tie-down and lifting
activities.
|
Company |
: TL
Offshore Sdn. Bhd. |
Position |
: Field Engineer |
Date |
September - October, 2002 |
Vessel: MV Vision III |
Client |
: Petronas
Carigali Sdn. Bhd. (Sabah, Malaysia) |
Project |
MLNG-Tiga - Pre-commissioning
of 32" dia. x 118 km SC3/E11R-C and 28" dia. x 3.5km
E11R-B/E11R-C Pipelines. |
|
- Pigging of 28" dia.
x 3.5km E11R-B/E11R-C pipeline.
- Bulk & Final dewatering
of 32" dia. x 118 km SC3/E11R-C and 28" dia. x 3.5km
E11R-B/E11R-C Pipelines.
- Spading works, jumper installation
& preparation work for vacum drying of both pipelines,
32" dia. x 118 km SC3/E11R-C and 28" dia. x 3.5km
E11R-B/E11R-C Pipelines.
|
Company |
: TL
Offshore Sdn. Bhd. |
Position |
: Field Engineer/Loadout
Coordinator |
Date |
: July 2002 |
Vessel : Container
Aquarius |
Client |
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: MLNG-Tiga E11R-C
Boatlanding Loadout at MSE, Pasir Gudang Johor, M'sia. |
|
- Loadout Coordinator. Coordinating
vessel movements for boatlanding & its shiploose transportation.
- Monitoring boatlanding loadout
to the material barge (Container Aquarius)
- Monitoring tie-down and lifting
activities.
- Ensure safety sailaway of
Container Aquaruis & its tug Mayang Sari
|
Company
|
: TL
Offshore Sdn. Bhd. |
Position
|
: Project/Field
Engineer |
Date
|
: May - June 2002 |
Vessel : DPDSV
Eagle |
Client
|
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: MASA Anode Retrofit. |
|
- Monitoring fabrication of
21 nos. of anode sleds at CMB, Pasir Gudang, Johore Malaysia.
- Vessel Inspection at Loyang,
Singapore.
- Coordinate with FPSO to ensure
safety and smooth operation during installation at FPSO turning
radius.
- Installation of anode sleds
at 12", 14" and 16" MASA Pipeline
|
Company |
: TL
Offshore Sdn. Bhd. |
Position |
: Field Engineer |
Date |
: Jan - April 2002 |
Vessel : -NA- |
Client |
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: MLNG-Tiga Trunkline
No. 5 & 6 |
|
- Assisting in preparation
of pipelay and beachpull procedure.
|
|
|
|
Company |
: TL
Offshore Sdn. Bhd. |
Position |
: Field Engineer |
Date |
: November 2001 |
Vessel : MV
Sea Panther |
Client |
: Sarawak
Shell Berhad. (Malaysia) |
Project |
: M3DR-A to M4 Manifold
14" Pipeline Precommissioning |
|
- Pre-commissioning 14"x10km
M3DR-A to M4 manifold pipeline
- Pigging, flooding, holding
pressure, depressurize & nitrogen packing.
|
Company
|
: TL
Offshore Sdn. Bhd. |
Position
|
: Field Engineer |
Date
|
: September 2001 |
Vessel : DSV
Ocean Winsertor |
Client
|
: Sarawak
Shell Berhad. (Malaysia) |
Project |
: SSB South Furious
2nd Phase |
|
- Riser & J-tube clamps
installation at F23DP-A and M3DR-A platforms
- Spool tie-in (riser to pipeline
and pipeline to subsea wellhead) at F23DP-A, M3DR-A, F23SW
& M4
- SCM (Subsea Control Module)
and UTHLB (Umbilical Termination Head Landing Base0 installation
at F23SW wellhead.
- Pre-Commissioning support
for F23DR-A to F23SW 12" pipeline.
|
Company
|
: TL
Offshore Sdn. Bhd. |
Position
|
: Field Engineer |
Date
|
: August 2001 |
Vessel : DB
30 |
Client
|
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: ANPG-A Topside
Installation |
|
- Complete installation of
2 MSFs (MSF North & MSF South), 5 nos. of modules (M2,
M3, M4, M5 & M6 living quaters), Helideck & 100m Bridge
connecting ANPG-A and ANDR-A platforms.
|
Company
|
: TL
Offshore Sdn. Bhd. |
Position
|
: Field Engineer |
Date
|
: July 2001 |
Vessel : DB
30 |
Client
|
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: ANPG-A Jacket (8
legged) |
|
- Complete installation of
8 legged jacket. Piling 32 nos. piles and installation of
8 nos. transition piece.
|
Company
|
: TL
Offshore Sdn. Bhd. |
Position
|
: Field Engineer/Loadout
Coordinator |
Date
|
: July 2001 |
Vessel : Intermac
403 |
Client
|
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: ANPG-A Jacket Loadout |
|
- Loadout coordinatior. Coordinating
vessel movements for jacket and piles transportation.
- Monitoirng jacket and piles
loadout to material barge.
- Monitoring tie-down and lifting
activities.
|
Company
|
: TL
Offshore Sdn. Bhd. |
Position
|
: Field Engineer |
Date
|
: June 2001 |
Vessel : MV
Seabulk Freedom |
Client
|
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: ANDP-B Remote Works |
|
- Installation of misc items
(i.e. conductor guides, stairs, gratings etc)
- Painting of transition piece
and touch up works.
|
Company
|
: TL
Offshore Sdn. Bhd. |
Position
|
: Field Engineer/Loadout
Coordinator |
Date
|
: June 2001 |
Vessel : Powerbarge
III |
Client
|
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: ANDP-B Topside
Loadout |
|
- Loadout at Brook Dock Yard
(BDWEC) Kuching.
- Loadout coordinator. Coordinationg
vessel movements for topside and conductors transportation.
- Monitoring topside loadout
(using bogey) and conductors loadout.
- Monitoring tie-down and lifting
activities.
|
Company
|
: TL
Offshore Sdn. Bhd. |
Position
|
: Field Engineer/Loadout
Coordinator |
Date
|
: March 2001 |
Vessel : Intermac
403 |
Client
|
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: ANDP-B Jacket Loadout |
|
- Loadout at Sime Sembawang
yard, Teluk Ramunia Johor, Malaysia.
- Loadout coordinator. Coordinating
vessel movements for jacket and piles transportation.
- Monitoring jacket and piles
loadout to material barge.
- Monitoring tie-down and lifting
activities.
|
|
|
|
Company |
: TL
Offshore Sdn. Bhd. |
Position |
: Field Engineer |
Date |
: November 2000 |
Vessel : MV
Vision 3 |
Client |
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: PFP Coating and
Candy Stripe Painting |
|
- PFP coating of 6 risers at
ANDR-A platform.
- Tiger stripe paintings of
6 risers at ANDR-A platform.
- Tiger strips paintings of
1 riser at GuD platform.
|
Company
|
: TL
Offshore Sdn. Bhd. |
Position
|
: QA Engineer |
Date
|
: July 2000 |
Vessel : MV
Seabulk Freedom |
Client
|
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: Pre-commissioning
of ANDR-A to GuD pipeline |
|
- Pre-commissioning job of
32" pipeline 56km ANDR-A platform to Guntong-D platform.
|
Company
|
: TL
Offshore Sdn. Bhd. |
Position
|
: QA Engineer |
Date
|
: May 2000 |
Vessel : -NA- |
Client
|
: Petronas
Carigali Sdn. Bhd. (Malaysia) |
Project |
: Various |
|
- Plan and maintains Quality
Assurance on project requirement.
- Perform internal quality
audit on assigned project.
- Verify that specifications
are met.
- Control inspection test plan
and check list.
- Control the material certificate.
- Control the equipment calibration
and certification.
- Control QA/QC documents on
assigned project.
|
|
|
|
Company |
: ZR Tech Enterprise |
Position |
: Computer Technician |
Date |
: 1998 to 1999 |
|
Client |
: Various |
Project |
: Various |
|
- PC assembly (software, hardware
& peripheral installation)
- Providing after sales service
and PC maintenance.
- Providing in-house training
for new staff.
|
Company |
:
Sabah Shell
Petroleum Company Ltd. |
Position |
: Trainee |
Date |
: 1998 |
|
Client |
: Various |
Project |
: Various |
|
- Study the overall company
operation/structure.
- Witness the Samarang &
Erb West pipeline pigging operation.
- Witness & understanding
the Free Water Knockout (FWKO) process, effluent/water treatment
plant (EWTP/ETP), sludge farm, storage tank and gas dehydration
process.
- Study the terminal utilities
i.e. air compressor, power generator & HVAC system.
- Witness the crude oil loading
operation from storage tank to oil tank via SBM (Single Buoy
Mooring.
- Assignment given- identify
the source of problem due to frequent generator trip off in
high temperature.
|
|
For
my detail resume, please contact laiman@crest.com.my
or call 6-017-3660466
|
|
|
|
Best view in
IE4+ with screen area 1024x768 pixels |
|
|
Employment Status |
Currently
I’m bonded with 1 year contract with TL Offshore Sdn.
Bhd. Start from 1st June, 2003 until 31st May, 2004. I’ll
only be available to the job market on the 1st June, 2004.
|
|